Eaton Lakeview Townhouses

 Eaton Street, Reading, MA

Construction Schedule



Demolition                         4/24/19  -    4/30/19


Site Preparation                 4/16/19   -   6/13/19


U.G. Sewer-Lakeview        6/13/19   -   11/1/19


U.G. Sewer-Eaton             6/29/19    -   11/1/19


Retaining Walls                4/29/19     -    6/1/20


Foundations                      7/30/20     -  10/20/20


U.G. Electrical                  10/9/20     -  10/17/20


Drains & Stormwater       10/20/20   -   11/12/20


Site Fine Grading              11/12/20   -   11/27/20


Eaton Sidewalk                 11/27/20   -   12/14/20


Building Rough                9/10/20     -       2/10/21


Units 1-2 

Wood Framing                  9/19/20     -     10/5/20


Building Envelope             10/5/20     -   10/21/20


Roof                                 10/5/20      -    10/14/20 


Deck                                 10/15/20    -  10/19/20


Front Stairs                      10/19/20   -  10/21/20


HVAC                               10/8/20     -  10/15/20


Plumbing                          10/10/20    - 10/17/20


Electrical                          10/14/20  -  10/23/20


Rough Inspections             10/17/20   -  10/27/20


Building Finish                  10/27/20 -   2/10/21  



Units 3-6 

Wood Framing                  10/21/21   -  11/14/20


Building Envelope             11/14/20     -   12/1/20


Roof                                  11/14/20     -  11/14/20


Deck                                 11/25/20    -  11/30/20


Front Stairs                      11/30/20   -   12/1/20


HVAC                               11/19/20   -   11/19/20


Sprinkler                          11/21/20     -    1/25/20


Plumbing                          11/21/20    -  11/28/20


Electrical                          11/27/20    -  12/8/20


Rough Inspections            11/26/20   -  12/12/20


Building Finish                12/12/20    -   3/11/21


Units 7-8 

Wood Framing                  11/19/20   -  12/14/20


Building Envelope             11/14/20     -  12/1/20


Roof                                  12/14/20  -   12/24/20


Deck                                 12/24/20    -  12/28/20


Front Stairs                      11/29/20  -   11/30/20


HVAC                               11/18/20   -   11/25/20


Plumbing                          12/19/20    -  12/28/20


Electrical                          12/25/20    -  12/2/20


Rough Inspections            12/28/20   -  1/6/21


Building Finish                  1/6/21 -     4/13/21


Units 9-12

Wood Framing                  12/21/20   -  1/14/21


Building Envelope             2/14/21     -   3/1/21


Roof                                  2/14/21     -  2/25/21


Deck                                 2/25/21      -  2/30/21


Front Stairs                      2/30/21     -   3/1/21


HVAC                               3/16/21     -   3/23/21


Sprinkler                          1/18/21     -     1/25/21


Plumbing                          1/18/21     -    1/25/21


Electrical                          1/25/21      -      2/4/21


Rough Inspections            1/23/21      -       2/10/21


Building Finish                  2/10/21    -        5/10/21 


 